耦合地质模型的TBM隧道施工过程进度仿真预测
徐琛1,刘晓丽1*,张鲁军2,毛宗原1,3,周建军4,5,王思敬1,6
1. 清华大学水沙科学与水利水电工程国家重点实验室, 北京 100084;2. 齐鲁交通材料技术开发有限公司, 山东 济南 250014;3. 中国建筑技术集团有限公司, 北京 100013;4. 盾构及掘进技术国家重点实验室, 河南 郑州 450001;5. 中铁隧道局集团有限公司, 广东 广州 511458;6. 中国科学院地质与地球物理研究所, 北京 100029
Simulation and prediction of TBM tunnel construction process coupling geological model
XU Chen1, LIU Xiaoli1*, ZHANG Lujun2, MAO Zongyuan1,3, ZHOU Jianjun4,5, WANG Sijing1,6
1. State Key Laboratory of Hydroscience and Engineering, Tsinghua University, Beijing 100084, China;
2. Qilu Transportation Materials Technology Development Co., Ltd., Jinan 250014, Shandong, China;
3. China Academy of Building Research, Beijing 100013, China;
4. State Key Laboratory of Shield Machine and Boring Technology, Zhengzhou 450001, Henan, China;
5. China Railway Tunnel Group Co., Ltd., Guangzhou 511458, Guangdong, China;
6. Institute of Geology and Geophysics, Chinese Academy of Sciences, Beijing 100029, China
下载:  PDF (3172KB) 
输出:  BibTeX | EndNote (RIS)      
摘要 基于隧道掘进机(tunnel boring machine, TBM)施工过程和施工工艺,融合三维地质建模技术和工程仿真技术,建立长隧道三维地质模型和施工循环网络仿真模型,实现长隧道TBM施工过程的可视化与施工进度的仿真预测。以西藏DXL隧道工程为研究对象,耦合DXL隧道三维地质模型,通过仿真计算对DXL隧道TBM施工段进度计划进行优化分析,统计拟合完工概率随施工工期变化的函数曲线,计算出预期完工概率,实现了施工过程的可视化,并提出保障施工进度的措施和建议。
服务
把本文推荐给朋友
加入引用管理器
E-mail Alert
RSS
作者相关文章
徐琛
刘晓丽
张鲁军
毛宗原
周建军
王思敬
关键词:  TBM施工  三维地质模型  循环网络模型  施工进度仿真  完工概率    
Abstract: Based on the analysis of the tunnel TBM construction process and technology, using the three-dimensional geological modeling technology and engineering simulation technology, a construction cycle network simulation model was established, which could achieve the prediction and visual analysis of TBM tunnel construction process. Taking the DXL tunnel project in Tibet as the research object, coupled with the three-dimensional geological model of the DXL tunnel, an optimized analysis of the TBM construction schedule of the DXL tunnel was performed through simulation calculations. The relationship between the completion probability and the construction time was fitted, and the expected completion probability was determined. The construction process was visualized and suggestions to guarantee the construction progress were proposed.
Key words:  TBM construction    three-dimensional geologic model    cycle network model    construction schedule simulation    probability of completion
                    发布日期:  2020-11-04      期的出版日期:  2020-11-04
中图分类号:  TV512  
  TP391  
基金资助: 国家重点研发资助项目(2018YFC1504902);水沙科学与水利水电工程国家重点实验室资助项目(2019-KY-03)
作者简介:  徐琛(1994— ),男,湖北黄冈人,博士研究生,主要研究方向为地下工程TBM掘进优化. E-mail:xuchen16@mails.tsinghua.edu.cn. *通信作者简介:刘晓丽(1978— ),男,山东泰安人,博士,教授,主要研究方向为岩土工程水岩作用及地下工程智能掘进. E-mail:xiaoli.liu@tsinghua.edu.cn
引用本文:    
徐琛,刘晓丽,张鲁军,毛宗原,周建军,王思敬. 耦合地质模型的TBM隧道施工过程进度仿真预测[J]. 隧道与地下工程灾害防治, 2020, 2(2): 41-46.
XU Chen, LIU Xiaoli, ZHANG Lujun, MAO Zongyuan, ZHOU Jianjun, WANG Sijing. Simulation and prediction of TBM tunnel construction process coupling geological model. Hazard Control in Tunnelling and Underground Engineering, 2020, 2(2): 41-46.
链接本文:  
http://tunnel.sdujournals.com/CN/Y2020/V2/I2/41
[1] 卓效明. 全断面隧道掘进机开挖与钻爆法开挖的比较[J]. 世界隧道, 1996(5): 32-38.
[2] 张镜剑, 傅冰骏. 隧道掘进机在我国应用的进展[J]. 岩石力学与工程学报,2007,26(2): 226-238. ZHANG Jingjian, FU Bingjun. Advances in tunnel boring machine application in China[J]. Chinese Journal of Rock Mechanics and Engineering, 2007, 26(2): 226-238.
[3] ABOURIZK S, MOHAMED Y. Optimal construction project planning[C] //Proceedings of the Winter Simulation Conference. San Diego, USA:IEEE, 2002:1704-1708.
[4] HOWART D F. Database of TBM projects undertaken between 1950 and 1990 and an assessment of associated ground-strength limitations[J]. Tunnelling and Underground Space Technology, 1994, 9(2): 209-213.
[5] LIU D H, XUAN P, LI S, et al.Schedule risk analysis for TBM tunneling based on adaptive CYCLONE simulation in a geologic uncertainty-aware context[J].Journal of Computing in Civil Engineering, 2015, 29(6): 04014103.
[6] 钟登华, 杨晓刚, 李景茹. 长隧洞TBM施工全过程仿真优化研究[J]. 水利水电技术, 2005,36(4):85-87. ZHONG Denghua, YANG Xiaogang, LI Jingru. Study on simulation and optimization of tunneling with TBM for long tunnel[J]. Water Resources and Hydropower Engineering, 2005, 36(4):85-87.
[7] 朱良峰, 潘信, 吴信才. 三维地质建模及可视化系统的设计与开发[J]. 岩土力学, 2006, 27(5): 828-832. ZHU Liangfeng, PAN Xin, WU Xincai. Design and development of 3D geological modeling and visualization system[J].Rock and Soil Mechanics, 2006, 27(5): 828-832.
[8] 李敏. 铁路隧道三维地质建模系统研究——隧道开挖和风险预警[D].成都:成都理工大学, 2009. LI Min. Study on 3D geological modeling of railway tunnel system—tunnel excavation and risk forewarning[D].Chengdu:Chengdu University of Technology, 2009.
[9] 刘东海, 黄培志. 隧洞TBM施工过程柔性循环网络建模与仿真分析[J]. 土木工程学报, 2010, 43(10): 115-121. LIU Donghai, HUANG Peizhi. Flexible cyclic operation network modeling and simulation analysis of TBM construction process[J].China Civil Engineering Journal, 2010, 43(10): 115-121.
[10] 刘振平. 工程地质三维建模与计算的可视化方法研究[D].武汉:中国科学院, 2010. LIU Zhenping. Study on technology of visualization in 3D engineering geological modeling and calculation[D]. Wuhan:the Chinese Academy of Sciences, 2010.
[11] 李卫兵. TBM在超长隧道施工中的应用研究[D].长春:吉林大学, 2005. LI Weibing. The application research of TBM on long tunnel[D]. Changchun: Jilin University, 2005.
[12] 杨晓刚. 复杂长隧洞TBM施工过程仿真优化研究[D].天津:天津大学, 2006. YANG Xiaogang. Research on simulation and optimization to TBM construction processes for long complex tunnels[D]. Tianjin:Tianjin University, 2006.
[13] JOHNSON D J. A spreadsheet method for calculating work completion time probability distributions of paced or linked assembly lines[J]. International Journal of Production Research, 2002, 40(5):1131-1153.
[1] 徐琛, 刘晓丽, 张鲁军, 毛宗原, 周建军, 王思敬. 耦合地质模型的TBM隧道施工过程进度仿真预测[J]. 隧道与地下工程灾害防治, 0, (): 1-7.
No Suggested Reading articles found!
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
网站版权 © 《隧道与地下工程灾害防治》编辑部
地址:山东省济南市山大南路27号山东大学中心校区明德楼B733《隧道与地下工程灾害防治》编辑部, 邮编:250100, 电话:0531-88366735, E-mail:tunnel@sdu.edu.cn
本系统由北京玛格泰克科技发展有限公司设计开发 技术支持:support@magtech.com.cn