Please wait a minute...
 
隧道与地下工程灾害防治
  研究论文 本期目录 | 过刊浏览 | 高级检索 |
沉管基槽开挖诱发临岸结构变形数值模拟与实测分析
刘力英,欧振锋*,杨春山,段尚磊
(广州市市政工程设计研究总院有限公司,广东 广州,510060)
Numerical simulation and field measurement analysis of coastal structures under immersed tunnel trench excavation
LIU Liying,OU Zhenfeng*,YANG Chunshan,Duan Shanglei
(Guangzhou Municipal Engineering Design & Research Institute Co., Ltd., Guangzhou 510060, Guandong,China)
下载:  PDF (998KB) 
输出:  BibTeX | EndNote (RIS)      
摘要 为揭示沉管基槽开挖卸荷作用下临岸结构变形特征,以广州如意坊放射线系统工程为背景,通过建立三维数值模型及进行现场监测对基槽开挖过程中临岸厂房与加强护岸变形规律展开分析。研究结果表明:基槽边坡坡面土体整体往基槽方向移动,沿基槽方向最大位移为23.65 mm,出现在边坡中间部位变坡点处;基槽开挖诱发厂房整体往河床方向倾斜,厂房位移随基槽开挖深度增加而增大并最终趋于稳定,数值结果与实测结果一致,实测厂房最大沉降为5.66 mm,数值计算厂房垂直堤岸方向位移最大值为8.13 mm,相邻柱基间沉降差与柱距之比最大值为0.264‰,满足规范限值要求,厂房运营安全;加强护岸变形以垂直堤岸方向为主,呈两端小中间大分布,最大为7.98 mm;坡顶设置钢板桩和基础注浆均可有效降低厂房结构变形,其中沉降降低效果显著,相比于未采取措施,同时设置钢板桩和注浆加固可降低厂房结构沉降约25%。研究成果可为城市中心区临岸工程建设周边建构筑物影响控制提供借鉴。
服务
把本文推荐给朋友
加入引用管理器
E-mail Alert
RSS
作者相关文章
刘力英
欧振锋
杨春山
段尚磊
关键词:  沉管隧道  基槽开挖  沉降监测  数值分析  变形控制措施    
Abstract: In order to reveal the deformation characteristics of the adjacent structures induced by immersed tunnel trench excavation, the Ruyifang Radioactive System Project in Guangzhou was taken as the background to analyze the deformation law of the adjacent plant buildings and the reinforced revetment during the foundation excavation by 3D-dimensional simulation and field measurement. The research results showed that: The soil on the slope surface of the foundation trench moved as a whole towards the direction of the foundation trench, with a maximum displacement of 23.65 mm along the direction of the foundation trench, occurring at the point of slope change in the middle of the slope; The excavation of the foundation trench induces the overall tilting of the factory building towards the riverbed, and the displacement of the factory building increased with the depth of the foundation trench excavation and eventually stabilized,the numerical results were consistent with the measured results,the maximum measured settlement of the factory building was 5.66 mm, and the maximum vertical displacement of the factory building in the direction of the embankment calculated numerically was 8.13 mm,the maximum ratio of the settlement difference between adjacent column foundations to the column spacing was 0.264 ‰, which met the requirements of the standard limit and ensured the safe operation of the factory building; The reinforced revetment deformed mainly in the vertical direction of the embankment with the variations of small at both ends and large in the middle and the maximum of 7.98 mm generating in the revetment top middle; The installation of steel sheet piles and foundation grouting at the top of the slope could effectively reduce the deformation of the factory structure, with a significant reduction in settlement. Compared with no measures taken, the simultaneous installation of steel sheet piles and grouting reinforcement could reduce the settlement of the factory structure by about 25%. The research results could provide reference for the impact control of buildings and structures under the construction of coastal engineering in the central area of the city.
Key words:  immersed tunnel    foundation excavation    settlement monitoring    numerical analysis    deformation control measure
收稿日期:  2024-08-30      修回日期:  2024-11-15      发布日期:  2024-11-15     
中图分类号:  TU433  
基金资助: 广东省住房和城乡建设厅科技创新计划资助项目(2022-K4-094918)
通讯作者:  欧振锋(1986—),男,湖南郴州人,工程师,博士,主要研究方向为岩土工程研究与设计。    E-mail:  ozf2010@163.com
作者简介:  刘力英(1978—),女,广东河源人,正高级工程师,硕士,主要研究方向为隧道与岩土工程。E-mail:37726157@qq.com
引用本文:    
刘力英, 欧振锋, 杨春山, 段尚磊. 沉管基槽开挖诱发临岸结构变形数值模拟与实测分析[J]. 隧道与地下工程灾害防治, .
LIU Liying, OU Zhenfeng, YANG Chunshan, Duan Shanglei. Numerical simulation and field measurement analysis of coastal structures under immersed tunnel trench excavation. Hazard Control in Tunnelling and Underground Engineering, 0, (): 1-11.
链接本文:  
[1] 王秋哲, 韩瑞, 白笑笑, 赵凯. 锁定回填下沉管隧道地震稳定性[J]. 隧道与地下工程灾害防治, 2023, 5(3): 71-77.
[2] 赵辰洋, 罗毛毛, 邱静怡, 倪芃芃, 赵锋烽. 盾构隧道施工引起地层变形预测方法综述[J]. 隧道与地下工程灾害防治, 2022, 4(3): 31-46.
[3] 王庆瀚,张恒臻,李克先. 大跨暗挖车站无柱中板结构内力分析及施工技术[J]. 隧道与地下工程灾害防治, 2020, 2(4): 83-90.
No Suggested Reading articles found!
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
网站版权 © 《隧道与地下工程灾害防治》编辑部
地址:山东省济南市山大南路27号山东大学中心校区明德楼B733《隧道与地下工程灾害防治》编辑部, 邮编:250100, 电话:0531-88366735, E-mail:tunnel@sdu.edu.cn
本系统由北京玛格泰克科技发展有限公司设计开发 技术支持:support@magtech.com.cn